Viewing Chicago Building Permit

General Information

The data is not guaranteed to be correct. It has been downloaded from City of Chicago Open Source Website.

All Permit Types

If you click one of the below buttons, you will need to use the Blue "Previous Page" button to get back here.

Statuses Milestones Types Reviews

Data Order

The data is shown in the Order of the Open Source File.

Since there are up to 15 Contacts per Permit, we decided to make a separate "Permit Contact" table.

If there are any contacts, they will be below this box. You may have to scroll down to see them.

Fees Related To This Permit

Building Fee Paid
$ 500.00
Zoning Fee Paid
$ 150.00
Other Fee Paid
$ 0.00
Subtotal
$ 650.00

Building Fee Unpaid
$ 0.00
Zoning Fee Unpaid
$ 0.00
Other Fee Unpaid
$ 0.00
Subtotal Unpaid
$ 0.00

Building Fee Waived
$ 0.00
Zoning Fee Waived
$ 0.00
Other Fee Waived
$ 0.00
Subtotal Waived
$ 0.00

Viewing Chicago Building Permit


Last Modified By Cuzmator: 2024-10-23 @ 3:43 PM
Permit #: 100728351
Permit Status: COMPLETE
Permit Milestone: COMPLETE
Permit Type: PERMIT - RENOVATION/ALTERATION
Review Type: STANDARD PLAN REVIEW
Application Start Date: 10/13/2017
Issue Date: 12/21/2017
Processing Time: 69
Address: 5150 W 55TH ST
PIN List: 1910320050
Work Type:
Work: LOW VOLTAGE FUEL MONITORING EQUIPMENT INSTALLATION AT EXISTING FUEL ISLAND FOR HERTZ RENTAL CAR(DOLLAR) MIDWAY AIRPORT.
Community Area: 56
Census Tract: 835200
Ward: 23
Location: POINT (-87.752119580929 41.793002855945)
Reported Cost: $ 37,715.00
X-Coordinate: 1142742.5788360715
Y-Coordinate: 1867696.5411072758
Latitude: 41.793002856
Longitude: -87.752119581
Attachment: No Attachment
Cook Viewer (Cook County GIS): External GIS Go
Contact Type Name
OWNER OCCUPIED THE HERTZ CORPORATION
ARCHITECT HUGGER ERIC J
CONTRACTOR-ELECTRICAL SHARLEN ELECTRIC COMPANY
EXPEDITOR HUGH EXPEDITING
CONTRACTOR-GENERAL CONTRACTOR K-PLUS MECHANICAL, INCORPORATED